Wednesday, December 1, 2010

KRU New Mosque as at 01 December 2010.

Main Dome with the crescent and the star.

Right view.

The frontage.

The right anjung.

Installing the roof trusses.

The Main Prayer Hall.


The Dome and the Minaret.

The anjung utama. (main entrance).

The Multipurpose Hall and the Mosque.

Side view of Multipurpose Hall.

Roofing and aluminum foil installed.

Open cooking and utility area.

Left view of the Mosque.

The Courtyard and the arches.

VIP Room with personalize washroom.

Mosque frontage closeup with Imam entrance.

Right view with the entrance arch.

The Mosque seen from Jalan Lengkongan.

Wiring work, finishing touches to the plaster surfaces, roofing to expose area and gravel filling for road tarmac is in progress.

The crescent and the star had been installed on the main Dome.

It had been observed and sad to note again that the Donation Safes for the New Mosque placed at the existing Mosque are being locked again by certain individual of the existing Mosque Committee. No one can donate for the good cause of the new Mosque anymore. Verbally nothing in black and white that stated the New Mosque Development Committee had been passed over to the existing Mosque Committee. It was agreed upon by the Authorities any donation collected for the New Mosque is to be transferred for safekeeping by MAIS (Majlis Agama Islam Selangor). What is happening now is anyone guesses.

My prediction for complete handover for the jemaah to utilize the New Mosque would be June 2011. The earliest would be April 2011.