Friday, May 6, 2011

KRU New Mosque as at 06 May 2011.

Rear view and potential parking tarmac.

Wak Selamat touching up.

Wak Suparjo with the long pole brush.

Incomplete Muslimah Wuduk area.

Waiting for roofing.

Left side of Main Prayer Hall had been roofed.

The main prayer Hall as it is.

Incomplete Muslimin Wuduk area.

The Dome and the Minaret.

the courtyard at the rear of main prayer hall.

Left side of the Mosque. Muslimah passageway.

View of Multipurpose hall from rear of Mosque.


Stagnant main septic tank.

Idle brick wall fencing.

The Anjung Utama.

Rear view of Mosque complex.

At a distance is Port Klang Crystal Crown Hotel.

The Dome glitters by the afternoon sun.

It was projected that the New Mosque would be completed by February 2011. The latest projection is now August 2011 and only 75% completion. Now is already May 2011.

Regret it would not see the kampong Jemaah performing the “tarawikh” in 2011 Ramadan and solat sunat Aidilfitri. Painting work is in progress and only four (4) Painters on site. Tiling work and roofing is here and there. The work on the main septic tank is currently stagnant. Wuduk area for Muslimin and Muslimah is in progress. Work on front and rear brick wall fencing currently suspended.

Don’t blame the Contractor as fund is not flowing, so how to complete?

Bearing no more hiccups and the weather fine all the way, hopefully and insyaalah, praise and doa to Allah swt, the New Mosque can be use by Aidiladha 2011. If the kampong residents could wait for ten (10) years, another few months should be no problem. Allah swt requests us to be patience (sabar) and there must be an “iktibar” (lesson/good reason) behind it.

Where has the state fund channel to?

No comment.