(Note: The high stores building at the background is Crystal Crown Hotel, Port Klang).
Mehrab craftsmen were nowhere to be seen but glad to note that they were busy at their Workshop and would transport the masterpieces to the Mosque for installation. I am anxious to see the full completion as the total cost is about RM 300+K.
Workers were busy laying interlocking brick paver on the left frontage of the Mosque. The main gate had been installed and the steel iron fencing painted.
Lines at parking area had been painted. Workers were painting the mid part of the minaret.
All bathroom, washroom and ablution area are ready awaiting installing of water piping.
The bunk to cleanse the demise is still stagnant.
My prediction of handover still remain June 2012 + and – two (2) months. Probably end of May 2012. There are plenty lot of things and minor work to be address.
Bearing all circumstances and teething problems, Jemaah of Kampong Raja Uda should be able to solat terawih and tedarus in the month of Ramadan in the New Mosque, sometimes July/ August 2012. Insyaalah.