Thursday, April 19, 2012

KRU New Mosque as at 19 April 2012.

It was this.

Now corrected to this.

Main prayer hall carpeted.

VIP Room carpeted.

Imam trying the Mimbar.

Quraan case.

Air condition vent at Imam Office.

Haji Ramlan testing the wuduk tap.

Yours truly.

Parking area with the water poodle.

Pantry.

Steel framing the courtyard arches.

The staircase to the Mimbar, carpeted.

Imam 2 – Tuan Haji Khairuddin, Haji Ramlan and me decided to enter the New Mosque complex to see the latest development.

The main entrance lettering of the signboard had been corrected.

Parking area – poodle of water from the overnight rain could be seen.

Carpeting at main prayer hall, completed. Carpeting also completed at Imam, Bilal area as well as VIP room and Mimbar. Air-condition units installed at Imam Office and Bilal waiting area.

Work is in progress installing steel frame with glasses at arches around the courtyard. I have no idea whether the same would be installed at all arches.

Water flowing all right from the taps at Muslimah ablution area but one shortcoming observed. Doors should be installed at the Muslimah ablution area as currently there is no privacy when Muslimah performing the ablution. The area is very well exposed to Jemaah walking along the corridor heading for the main prayer hall.

The pantry is also ready and completed.

I took the opportunity to solat dhuha and perhaps I am one of the first, beside the construction workers to pray inside the Mosque.

The mosque construction is nearing to the finishing tape and a lot of minor things to be address before commissioning. Tentatively, by June 2012 should be all right.



No comments: