Wednesday, July 27, 2011

KRU New Mosque as at 27 July 2011.

Last posting for July 2011.




The Mosque from various angles.

Ceilings to be installed.

Ceilings frame installed.


Some progress on the Mimbar.

Installing the aluminum frame of the ceilings.

Tilings almost completed all round.

Situation of the Main septic tank.

I would be away for forty (40) days from the community and would not be able to follow the development during August 2011.

It is for sure that the New Mosque would not be completed for Ramadan and solat sunat Aidilfitri. From reliable sources on site, it is expected to complete within two (2) months time. I reckon, plus minus, it would be within six (6) months from now.

The snaps taken as of today, 27 July 2011 afternoon would tell the latest situation.

Packing off to KLIA.



No comments: