KRU New Mosque as at 05 March 2011.

The only incomplete part.

The brick walling fencing (East entrance).

View from the east.

Ceiling the Multipurpose Hall. The holes are for lighting.

Provisional gate for the Jalan Puspa residents.

The Moorish arches of the Mosque corridors.

The Dome and the minaret.

The courtyard and the main prayer hall.

The pigeon hole elevated Mimbar and the Imam pulpit.

Side view of Minaret.

Frontage view of Mosque.

It was projected to complete by February 2011 but now it’s already beginning of March 2011 the New Mosque is far from completion. Why? It’s anybody guess. It’s none of my business. I merely record the progress in portraits.

The pictures above will tell no lies that the structural building of the New Mosque is near completion.

Wiring work is aggressively in progress. Brick walling fencing of the east and west perimeter is in progress and the north and south chain link completed. Provision made for a small gate for the Jalan Puspa residents access at the south perimeter. Ceiling work is in progress at the open covered area near the Cafeteria. The Laborers Quarters had been relocated to make way for tarmac surfacing and brick walling fencing at the Mosque frontage.

My present projection is May or June 2011. Whatever, I hope and pray that the New Mosque can be use during Ramadan that will be August 2011. Insyaalah.